- Excavation and Site Preparation: Excavation works were carried out for the installation of pole foundations, taking measures to ensure the stability and durability of the structures.
- Pole Installation: Pre-stressed spun concrete poles were installed, providing high durability and stability for the overhead lines.
- Conductor Installation: AL-STEEL conductors were laid for electric power transmission, ensuring stable and efficient connections between different network points.
- Accessory Installation: Insulators, 20 kV three-pole disconnectors, and other protective devices were installed to guarantee the safe operation of the line.
Installation of “BOX”-Type Substations
- Manufacturing and Transport: The “BOX”-type substations were manufactured in accordance with technical specifications and transported to the installation site.
- Positioning on Site: The substations were installed on pre-prepared foundations, ensuring proper leveling and anchoring to guarantee structural stability.
- Internal Equipment Assembly: Inside the substations, line switches, transformer switches, and low-voltage distribution panels were installed, ensuring the necessary electrical and mechanical connections.
Testing and Commissioning
- Quality Control: Tests were performed to verify the integrity of the installations and to ensure that all components functioned according to project specifications.
Commissioning: After the completion of testing, the system was put into operation and monitored over a defined period to ensure its stable and efficient performance.