Water Supply System.
Client
National Agency for Water Supply.
Industry
HEC
PROJECT SCOPE
Construction
YEAR / DURATION
6 months
Project Description
Replacement of the existing deteriorated transmission line from the Bambull Pumping Station to the reservoirs in Memaliaj.
Ensuring 24-hour water supply to the Memaliaj reservoir with adequate pressure and water quality in compliance with Albanian and European Union (EU) standards.
Installation of water meter boxes for the apartments of 32 residential buildings in the city of Memaliaj.
Executed Works
As part of the water supply project for the city of Memaliaj, the following key phases have been successfully completed:
• Excavation for the extension of the water supply network
• Installation of PE100 pipes and hydraulic accessories
• Installation of water meters for subscribers
• Topographic and geodetic works during project implementation
• Construction of masonry structures and infrastructure protection
• Complete testing and commissioning of the water supply system
• Rehabilitation of affected areas and restoration of infrastructure to its original condition
The network is now operational, ensuring a stable and continuous water supply for the city.